Project roundup: The following oil and gas pipeline jobs have been announced. Projects are in order of  most recent approximate starting date. All projects are for 2017 unless noted.

The Hillis Group LLC was awarded a contract by Williams for tree removal, clearing and restoration on approximately 26 miles of 30-in. pipeline right of way in Allegheny County, Pennsylvania. Headquarters is Gibson, Pennsylvania. The superintendent is Josh Kunes. Approximate start date: April 3.

InfraSource LLC was awarded a contract by Ameren Illinois to install approximately 800 ft of 12-in. pipeline and 1,120 ft of 8-in. pipeline in Brown and Knox counties, Illinois. Headquarters is Litchfield, Illinois. The superintendent is Clark DeGroot. Approximate start date: April 1.

Indianhead Pipeline Services LLC was awarded a contract by U.S. Pipeline Inc. for foam work on approximately 19 miles of dual 42-in. pipeline, approximately 33 miles of single 42-in. pipeline and 3 miles of 30-in. pipeline in Harrison, Carroll and Belmont counties, Ohio. Headquarters is to be determined. The superintendent is Randy Rubenzer. Approximate start date: April 1.

Northern Clearing Inc. was awarded a contract by Precision Pipeline LLC for clearing approximately 51 miles of 20- and 16-in. pipeline right of way in Perry, Cumberland, York and Dauphin counties, Pennsylvania. Headquarters is to be determined. The superintendent is Duanne Kmieciak. Approximate start date: April 1.

Penn Line Service Inc. was awarded a contract by Rockford Corporation for the hydroseeding on approximately 4 miles of 30-in. pipeline right of way in Susquehanna County, Pennsylvania and Broome County, New York. Headquarters is on the jobsite. The superintendent is Jim Pratt. Approximate start date: April 1.

BigInch Fabricators and Construction Inc. was awarded a contract by Panhandle for the hydrotesting of approximately 5 miles of 26-in. pipeline in Douglas County, Illinois. Headquarters is the Tuscola Panhandle Station. The superintendent is Chris Elliott. Approximate start date: March 22.

Ace Pipeline Inc. was awarded contract by EQT to install approximately 46,000 ft of 20-in. pipeline and approximately 26,700 ft of 12-in. pipeline in Doddridge and Ritchie counties, West Virginia. Headquarters is West Union, West Virginia. The superintendent is Sam Jarvis. Approximate start date: March 21.

Apex Pipeline Services Inc. was awarded a contract by MarkWest for tree cutting on approximately 20,000 ft of 30-in. pipeline right of way in Doddridge County, West Virginia. Headquarters is Sherwood, West Virginia. The superintendent is Randy Epling.
Approximate start date: March 20.

Foltz Welding Ltd. (d/b/a continental Pipeline Services) was awarded a contract by Energy Transfer Trunkline Gas for a meter station upgrade consisting of approximately 280 ft of 36-in. pipeline, approximately 800 ft of 30-in. pipeline, approximately 100 ft of 26-in. pipeline, approximately 150 ft of 12-, 10- and 8-in. pipeline and approximately 1,000 ft of small bores in Douglas County, Illinois. Headquarters is Patoka and Bourbon, Illinois. The superintendent is Tim Rinehart. Approximate start date: March 20.

Henkels & McCoy Inc. was awarded a contract by Williams Transco for the construction of a meter station in Union County, New Jersey. Headquarters is Linden, New Jersey. The superintendent is Tubby Long. Approximate start date: March 20.

Indianhead Pipeline Services LLC was awarded a contract by Precision Pipeline LLC for buoyancy control, foam and seeding work on approximately 420 miles of 42-, 36-, 30- and 24-in. pipeline in various counties in Ohio, Michigan and West Virginia. Headquarters is to be determined. The superintendent is Randy Rubenzer. Approximate start date: March 20.

MDS Boring & Drilling Inc. was awarded a contract by U.S. Pipeline Inc. for road boring of approximately 18 miles of 42-in. pipeline consisting of 56 road bores and totaling 2,660 ft in Harrison County, Ohio. Headquarters is U.S. Pipeline yard. The superintendent is Randy Cassell. Approximate start date: March 20.

Precision Pipeline LLC was awarded a contract by Sunoco to install approximately 51.4 miles of 20-in. pipeline in Cumberland, York and Dauphin counties, Pennsylvania. Headquarters is to be determined. The superintendent is Ronnie Michalkovich. Approximate start date: to be determined (announced March 20).

Brandenburg Drainage Inc. was awarded a contract by Alliance Pipeline for the repair of a test lead, installation of a test lead and the installation of a dual coupon test station in Grundy and Bureau counties, Illinois. Headquarters is to be determined. The superintendent is Art Brandenburg. Approximate start date: March 16.

Indianhead Pipeline Services LLC was awarded a contract by Precision Pipeline LLC for cleanup on approximately 4 7 miles, seeding on approximately 88 miles and punchlist work on approximately 508 miles of 30-in. pipeline in various counties in Illinois and Iowa. Headquarters is to be determined. The superintendent is Brian Proud. Approximate start date: March 15.

Appalachian Pipeline Contractors LLP was awarded a contract by Piedmont Natural Gas for the replacement of approximately 2.5 miles of 10-in. pipeline in New Hanover County, North Carolina and 30” insulator work at a compressor station in Cabarrus County, North Carolina. Headquarters is to be determined. The superintendent is Ben Gruetzmacher. Approximate start date: March 13.

B&N Clearing and Environmental LLC was awarded a contract by Price Gregory International Inc. for clearing of approximately 3 miles of 36-in. pipeline right of way in Lawrence County, Ohio and Wayne County, West Virginia. Headquarters is to be determined. The superintendent is Kevin Newcomb. Approximate start date: March 13.

BigInch Fabricators and Construction Inc. was awarded a contract by Truckline for a long wall mine project excavating approximately 2,000 ft of each 36-, 30- and 26-in. pipelines in Hamilton County, Illinois. Headquarters is Montezuma, Indiana. The superintendent is Brent Shepler. Approximate start date: March 13.

The HDD Company Inc. was awarded a contract by Precision Pipeline LLC for approximately 10,000 ft of 42-in. horizontal directional drilling bores in Ashland and Seneca counties, Ohio. Headquarters is on the jobsites. The superintendent is Neil Swope. Approximate start date: March 13.

Hoover Construction Company was awarded a contract by U.S. Pipeline Inc. for drilling and blasting operations on approximately 69.74 miles of 42-in. pipeline in Belmont, Monroe, Harrison and Carrol counties, Ohio. Headquarters is Dennison, Ohio. The superintendent is Gus Jones. Approximate start date: March 13.

Pe Ben USA Inc. was awarded contracts by Precision Pipeline LLC for the loading, hauling and stringing of the following: 1.) approximately 70 miles of 42-in. pipe in Carroll, Tuscarawas, Stark and Wayne counties, Ohio. The superintendent is Tommy Haynes; 2.) approximately 85 miles of 42-in. pipe in Ashland and Wayne counties, Ohio. The superintendent is J.W. Morgan; 3.) approximately 85 miles of 42-in. pipe in Richland, Crawford, Seneca and Hancock counties, Ohio. The superintendent is Cory Strandlien; 4.) approximately 165 miles of 42-in. pipe in Hancock, Wood, Henry, Defiance and Fulton counties, Ohio and Lenawee County, Michigan. The superintendent is Toby Prawl; 5.) approximately 17 miles of 42-in. pipe and approximately 4 miles of 24-in. pipe in Monroe and Noble counties, Ohio. The superintendent is Adam Minigh; and 6.) approximately 9 miles of 42-in. pipe and approximately 18 miles of 36-in. pipe in Monroe County, Ohio. The superintendent is Chane Keeling. Headquarters are in Massillon and Mansfield, Ohio and Monroe, Michigan. Approximate start date: March 13 (for all).

Price Gregory International Inc. was awarded a contract by TransCanada/Columbia Pipeline Group to install approximately 15,348 ft of 36-in. pipeline in Lawrence County, Ohio and Wayne County, West Virginia. Headquarters is Ashland, Kentucky. The superintendent is Gary Pellham. Approximate start date: March 13.

Eastern Shore Natural Gas Co. received FERC approval to place into service the Delaware City Compressor Station in New Castle County, Delaware into service. The station is part of the White Oak Mainline Expansion Project. Approval was granted March 10.

T.G. Mercer Consulting Services Inc. was awarded a contract by Welspun Tubular LLC for the offloading and racking of approximately 24 miles of 42-in. pipe in Braxton and Nicholas counties, West Virginia. Headquarters is Willow Park, Texas. The superintendent is Michael Magee. Approximate start date: March 8.

Supreme Industries was awarded a contract by Henkels & McCoy Inc. for clearing of approximately 2,500 ft of 42-in. pipeline right of way in Middlesex County, New Jersey. Headquarters is Keyport, New Jersey. The superintendent is Galen Boucher. Approximate start date: March 7.

Minnesota Limited LLC was awarded a contract by Vectren for integrity maintenance work consisting of boring and fitting replacements of 16-in. pipeline sections and pipeline valve replacements of various sizes up to 12-in. in Posey and Vanderburgh counties, Indiana. Headquarters is Evansville, Indiana. The superintendent is Greg Frazier. The starting date is to be determined (announced March 6).

Price Gregory International Inc. was awarded a contract by Kinder Morgan/Tennessee Gas Pipeline Company LLC to install approximately 15.1 miles of 36-in. pipeline in Susquehanna and Tioga counties, Pennsylvania. Headquarters is Welsboro, Pennsylvania. The superintendent is Lack Burch. Approximate start date: March 6.

Snelson Companies Inc. was awarded a contract by Pacific Gas & Electric for replacement of an 8-in. pipeline valve in San Bernardino County, California. Headquarters is to be determined. The superintendent is Shaun Dewey. Approximate start date: March 6.

B&N Clearing and Environmental LLC was awarded a contract by Price Gregory International Inc. for the hand felling of timber on approximately 15 miles of 36-in. pipeline right of way in Susquehanna and Tioga counties, Pennsylvania. Headquarters is Wellsboro, Pennsylvania. The superintendent is Kevin Newcomb. Approximate start date: March 3.

Henkels & McCoy Inc. was awarded a contract by AGL to install approximately 620 ft of 12-in. pipeline and a regulator meter station in Murray County, Georgia. Headquarters is Calhoun, Georgia. The superintendent is Scott Schoenherr. Approximate start date: March 3.

Share.

Comments are closed.