The following oil and gas pipeline projects have been announced. Pipeline Project Roundup listings are in order of most recent approximate starting date. All projects are for 2019 unless noted.

The Hillis Group LLC was awarded a contract by Williams for a 24-in. pipeline cutout in Clinton County, Pennsylvania. Headquarters is Linden, Pennsylvania. The Superintendent is Bill Adams. Approximate start date: March 25.

Pe Ben USA Inc. was awarded a contract by Berg Pipe for the offloading from rail and stockpiling of approximately 3.5 miles of 36-in. pipe in Polk County, Florida. Headquarters is Lake Wales, Florida. The superintendent is Jimmy Gregory. Approximate start date: March 25.

Dun Transportation & Stringing Inc. was awarded a contract by Welspun to offload and stockpile approximately 425 miles of 42-in. pipe in Pecos, Irion, Kimble, Blanco and Gonzalez counties, Texas. Headquarters are the pipe yards. The superintendents are Mike Bruce and Johnny Denton. Approximate start date: March 18.

Foltz Welding Ltd. d/b/a Continental Pipeline was awarded a contract by Spire St. Louis Pipeline for the installation of a new 24-in. pipeline meter station in St. Louis County, Missouri. Headquarters is Spanish Lake, Missouri. The superintendent is Mike Jeffords. Approximate start date: March 18.

/*** Advertisement ***/

U.S. Pipeline Inc. was awarded a contract by Williams for the installation of an additional 30,000-hp compressor and piping modifications on an existing meter station in Essex and Passaic counties, New Jersey. Pipe size will vary from 1- to 42-in. pipelines. Headquarters is Roseland, New Jersey. The superintendent is Todd Strassburg. Approximate start date: March 18.

T.G. Consulting Services Inc. was awarded a contract by American Steel for the offloading and racking of approximately 81,000 ft of 24-in. pipe in Ward and Winkler counties, Texas. Headquarters is Willow Park, Texas. The superintendent is Larry Rodriguez. Approximate start date: March 18.

T.G. Mercer Consulting Services Inc. was awarded a contract by Epic for the offloading and racking of approximately 230 miles of 30-in. pipe in Nueces and LaSalle counties, Texas. Headquarters is Willow Park, Texas. The superintendent is Larry Rodriguez. Approximate start date: March 15.

T.G. Mercer Consulting Services Inc. was awarded a contract by Phillips 66 for the handling of materials in Live Oak and Ward counties, Texas. Headquarters is Willow Park, Texas. The superintendent is Larry Rodriguez. Approximate start date: March 15.

BigInch Fabricators & Construction Inc. was awarded a contract by Energy Transfer for the excavation of 2- to 24-in. pipelines in Washtenaw County, Michigan. Headquarters is Montezuma, Indiana. The superintendent is Steve Enerson. Approximate start date: March 14.

Price Gregory International Inc. was awarded a contract by Piedmont Natural Gas Company Inc. to perform maintenance on existing 2- to 20-in. pipelines, including, but not limited to, anomaly digs, replacement of lines, metering and regulations stations and emergency services in Warren, Butler, Clinton, Clermont, Brown, Adams and Hamilton counties, Ohio, and Boone, Kenton, Campbell, Gallatin, Grant, Pendleton and Bracken counties, Kentucky. Headquarters is Woodlawn Ohio. The superintendent is Darryl Ditterline. Approximate start date: March 11.

Dun Transportation & Stringing Inc. was awarded a contract by MPG to haul approximately 90 miles of 30-in. pipe and approximately 10 miles of 16-in. pipe in Live Oak and San Patricio counties, Texas. Headquarters is the pipe yard. The superintendent is Rick Perrington. Approximate start date: March 4.
Minnesota Limited LLC was awarded a contract by Vectren for the replacement of approximately 7,400 ft of 20-in. pipeline, launcher and receiver replacements and station upgrades in Montgomery and Greene counties, Ohio. Headquarters is to be determined. The superintendent is Mark Carpenter. Approximate start date: March 4.

Henkels & McCoy Inc. was awarded a contract by TransCanada for the take up and re-lay of approximately 2,800 ft of 36-in. pipeline in Iron County, Wisconsin. Headquarters is Saxon, Wisconsin. The superintendent is Andy Durkin. Approximate start date: Feb. 27.

T.G. Mercer Consulting Services Inc. was awarded a contract by EPCO for the offloading and racking of approximately 19 miles of 24- and 30-in. pipe in Ward County, Texas. Headquarters is Willow Park, Texas. The superintendent is Larry Rodriguez. Approximate start date: Feb. 25.

Maxx HDD LLC was awarded a contract by Venables Construction for various 30-in. road bores and horizontal directional drills in Waller, Austin and Washington counties, Texas. Headquarters is Sealy, Texas. The superintendent is James Bond. The approximate starting date was Feb. 21.

Northern Clearing Inc. was awarded a contract by Price Gregory International Inc. for limited tree clearing on approximately 43 miles of 6-, 10- and 20-in. pipeline right-of-way in Marquette County, Michigan. Headquarters is to be determined. The superintendent is Jim Junker. The approximate starting date was Feb. 20.

Snelson Companies Inc. was awarded a contract by Pacific Gas & Electric the installation of approximately 500 ft of various size pipelines in Alameda County, California. Headquarters is Fremont, California. The superintendent is Shaun Dewey. The approximate starting date was Feb. 19.

Apex Pipeline Services Inc. was awarded a contract by Williams for the installation of approximately 7.5 miles of 24-in. pipeline in Marshall County, West Virginia. Headquarters is Glendale, West Virginia. The superintendent is Roman McKnown. The approximate starting date was Feb. 18.

Apex Pipeline Services Inc. was awarded a contract by Williams for the installation of approximately 7.5 miles of 24-in. pipeline in Marshall County, West Virginia. Headquarters is Triadelphia, West Virginia. The superintendent is Moe Riddle. The approximate starting date was Feb. 18.

Atlas Trenchless LLC was awarded a contract by Michels Corporation the installation of approximately 1,000 ft of 16-in. pipeline via horizontal directional drill in Blair County, Pennsylvania. Headquarters is Rockville, Minnesota. The superintendent is Jim Lagios. The approximate starting date was Feb. 18.

B & N Clearing and Environmental LLC was awarded a contract by Price Gregory International Inc. for right-of-way clearing and associated activities on approximately 10.3 miles of 42-in. pipeline right-of-way in Chilton and Choctaw counties, Alabama. Headquarters is to be determined. The superintendent is Kevin Newcomb. The approximate starting date was Feb. 16.

Right-of-Way Clearing & Maintenance Inc. was awarded a contract by Apex Pipeline Services Inc. for clearing on approximately 13.94 miles of 24-in. pipeline in Marshall County, West Virginia. Headquarters is Glen Dale, West Virginia. The superintendent is Orvil Davis. The approximate starting date was Feb. 11.

Dun Transportation & Stringing Inc. was awarded a contract by Strike for the loading and hauling of miscellaneous bore pipe in Kingfisher and Carter counties, Oklahoma. Headquarters is the pipe yard. The superintendent is Greg Norman. The approximate starting date was Feb. 4.