North American Pipeline Project Roundup: September 2018

0

The Project Roundup provides a glimpse of the oil and gas pipeline projects have been announced. Projects are in order of most recent approximate starting date. All projects are for 2018 unless noted.

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric to install approximately 1,400 ft of 4-in. natural gas pipeline in San Juaquin County, California. Headquarters is not yet determined. The superintendent is Chris Sullivan. Approximate start date: Aug. 6.

United Piping Inc. was awarded contracts by Enbridge for 1.) the expansion of a 36-in. pipeline compressor station in Belmont County, Ohio. Headquarters is Dillonvale, Ohio. The superintendent is Larry Wright; and 2.) the painting of 4-in. station piping in Lake County, Indiana. Headquarters is not yet determined. The superintendent is Joel Bailer. Approximate start dates: 1.) July 26 and 2.) Aug. 2.

Brush Cutters LLC was awarded a contract by Otis Eastern Service LLC for the clearing of approximately 14 miles of 12-in. pipeline right-of-way in McKean County, Pennsylvania. Headquarters is not yet determined. The superintendent is Greg Hoppel. Approximate start date: Aug. 1.

United Piping Inc. was awarded a contract by ONEOK for the take-up and re-lay of approximately 2,700 ft of 30-in. pipeline in Simpson County, Kentucky. Headquarters is on the jobsite. The superintendent is Tim Darif. Approximate start date: Aug. 1.

BigInch Fabricators & Construction Inc. was awarded a contract by Midwestern Gas- ONEOK to replace a 24-in. crossover in Pike County, Indiana. Headquarters is Montezuma, Indiana. The superintendent is not yet determined. Approximate start date: unknown (announced July 30).

T.G. Mercer Consulting Services Inc. was awarded a contract by Energy Transfer for pipe yard clean-up in Beaver County, Pennsylvania. Headquarters is Willow Park, Texas. The superintendent is Michael Magee. Approximate start date: July 30.

United Piping Inc. was awarded a contract by BP Pipelines for the inspection of 12-in. and under station piping in Marion County, Illinois. Headquarters is on the jobsite. The superintendent is Jim Bailer. Approximate start date: July 26.

Moosehead Harvesting Inc. was awarded a contract by Meridien Energy LLC for the clearing of approximately 4 miles of 20-in. pipeline right-of-way in Doddridge County, West Virginia. Headquarters is New Milton, West Virginia. The superintendent is Robert Reed Jr. Approximate start date: July 23.

United Piping Inc. was awarded a contract by TransCanada for integrity digs on a 26-in. pipeline in Loudoun and Fairfax Counties, Virginia for TransCanada. Headquarters is on the jobsite. The superintendent is Joel Bailer. Approximate start date: July 23.

Clearwater Construction Inc. was awarded a contract by Appalachian Pipeline Contractors LLP for approximately 1,000 ft of road crossing repair in Chester County, Pennsylvania. Headquarters is Mercer, Pennsylvania. The superintendent is Bruce Miller. Approximate start date: July 16.

Dun Transportation & Stringing Inc. was awarded a contract by EVRAZ for the unloading, hauling and stockpiling of approximately 102 miles of 36-in. pipe in Carter County, Oklahoma. Headquarters is the pipe yard. The superintendent is Greg Norman. Approximate start date: July 30.

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric to install approximately 4,500 ft of 8-in. and 12-in. pipeline in Santa Cruz County, California. Headquarters is not yet determined. The superintendent is Jack Symonds. Approximate start date: July 30.

Right-of-Way Clearing & Maintenance Inc. was awarded a contract by Precision Pipeline LLC for clearing on approximately 12 miles of 42-in. pipeline right-of-way in Braxton and Webster counties, West Virginia. Headquarters is Sutton, West Virginia. The superintendent is Orvil Davis. Approximate start date: June 27.

InterCon Construction Inc. was awarded a contract by MarkWest to install approximately 9,949 ft of 12-in. pipeline in Jefferson County, Ohio. Headquarters is Mingo Junction, Ohio. The superintendent is Joey Wade. Approximate start date: July 25.

Pe Ben USA Inc. was awarded a contract by Rockford Corp. for the hauling and stringing of approximately 10 miles of 42-in. pipe in Randolph and Monongalia counties, West Virginia. Headquarters is Valley Head, West Virginia. The superintendent is Ed “Bucky” Reed. Approximate start date: July 23.

Snelson Cos. Inc. was awarded a contract by Northwest Pipeline LLC (Williams) to replace approximately 3,770 ft of 22-in. pipeline, hydrotest approximately 77,660 ft of 22-in. pipeline, install a 22-in. pipeline mainline valve, and replace a 16-in. valve in Ada, Canyon, Gem and Payette counties, Idaho, and Malheur County in Oregon. Headquarters is Greenleaf, Idaho. The superintendent is William Hank Sullivent and Cody Gay. Approximate start date: July 23.

United Piping Inc. was awarded two contracts by BP Pipelines for: 1.) approximately 3 0 ft on 10-in. of mainline maintenance in Dubuque County, Iowa. Headquarters is on the jobsite. The superintendent is Jim Bailer; and 2.) pipeline inspection in Shelby County, Illinois on less than one mile at the station on 12-in. and under pipeline. Headquarters is on the jobsite. The superintendent is Jim Bailer. Approximate start dates: 1.) July 23 and 2.) July 20.

United Piping was awarded a contract by TransCanada for various digs on a 26-in. pipeline in Loudoun and Fairfax Counties, Virginia. Headquarters is on the jobsite. The superintendent is Joel Bailer. Approximate start date: July 23.

U.S. Pipeline, Inc. was awarded a contract by TransCanada to replace approximately 5,000 ft of 20-in. and 24-in. pipeline in three separate locations in Adams County, Pennsylvania. Headquarters is Gettysburg, Pennsylvania. The superintendent is Dana Bratcher. Approximate start date: July 23.

Pe Ben USA Inc. was awarded contracts by TransCanada KXL for 1.) the inspection and repair of 375 miles of 36-in. pipe in Bowman County, North Dakota. Headquarters is Gascoyne, South Dakota. The superintendent is not yet determined; and 2.) pipe yard construction and the offloading and stockpiling 90 miles of 36-in. pipe in Union County, South Dakota. Headquarters is Mad Butte, South Dakota. The superintendent is not yet determined. Approximate start dates: 1.) July 12 and 2.) July 20.

United Piping was awarded a contract by Enbridge for the expansion of a 36-in. pipeline compressor station in Belmont County, Ohio. Headquarters is Dillonvale, Ohio. The superintendent is Larry Wright. Approximate start date: July 18.

Dun Transportation & Stringing Inc. was awarded a contract by Enterprise for the unloading of approximately 10 miles of 30-in. pipe in Patoka, Illinois. Headquarters is the pipe yard. The superintendent is Mike Bruce. Approximate start date: July 16.

InfraSource LLC was awarded a contract by Mears Group Inc./Duke Energy for 12 pipeline anomaly digs in Clermont County, Ohio. Headquarters is not yet determined. The superintendent is Jeff Lauritzen. Approximate start date: July 16.

InterCon Construction Inc. was awarded a contract by Mark West to install 32,002 ft of 12-in. pipeline in Guernsey County, Ohio. Headquarters is not yet determined. The superintendent is Joey Wade. Approximate start date: July 16.

Max HDD LLC was awarded a contract by U.S. Pipeline Inc. for one 30-in. pipeline road bore in Columbia County, Ohio. Headquarters is Hanoverton, Ohio. The superintendent is Brad Vickers. Approximate start date: July 16.

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric for the hydrotesting of 56 miles of 12-in. pipeline in San Bernardino County, California. Headquarters is not yet determined. The superintendent is Trevor Payne. Approximate start date: July 16.

T.G. Mercer Consulting Services Inc. was awarded a contract by Epic for the offloading and racking of approximately 23 7 miles of 24-in. pipe in LaSalle County, Texas. Headquarters is Willow Park, Texas. The superintendent is Michael Magee. Approximate start date: July 15.

B&N Clearing and Environmental LLC was awarded a contract by Welded Construction LP for the clearing of 2.5 miles of 36-in. pipeline right-of-way associated with the construction of Spread 1 of the TransCanada Mountaineer Express Pipeline Project in Marshall and Wetzel Counties, West Virginia. Headquarters is New Martinsville, West Virginia. The superintendent is Kevin Newcomb. Approximate start date: July 12.

Tom Allen Construction Co. was awarded a contract by Columbia Gas of Virginia to replace approximately 9,500 ft of 8-in. pipeline in Chesterfield County, Virginia. Headquarters is Chester, Virginia. The superintendent is Stanley West. Approximate start date: July 11.

Schmid Pipeline Construction Inc. was awarded a contract by Welded Construction LP for excavation work on a 20-in. pipeline in Washington County, Pennsylvania. Headquarters is Washington, Pennsylvania. The superintendent is Lonnie Skadsen. Approximate start date: July 10.

Ellingson Trenchless LLC was awarded a contract by Rockford Corp. for a 12-in. pipeline horizontal directional drill in Okeechobee County, Florida. Headquarters is on the jobsite. The superintendent is unknown. Approximate start date: unknown (announced July 9).

Henkels & McCoy Inc. was awarded a contract by Williams Transcontinental for the recommissioning of Williams-West Diamond Meter Station in Columbia County, Pennsylvania. Headquarters is Sweet Valley, Pennsylvania. The superintendent is Gary Seidel. Approximate start date: July 9.

Letourneau Enterprises LLC was awarded a contract by U.S. Pipeline Inc. for clearing, grubbing and matting on approximately 17.59 miles of 42-in. pipeline right-of-way in Pocahontas and Randolph counties, West Virginia and Highland and Bath counties, Virginia. Headquarters is Marlinton, West Virginia. The superintendent is Jason W. Mack. Approximate start date: July 9.

Letourneau Enterprises LLC was awarded a contract by Snelson Cos. Inc. for the clearing, grubbing and matting of approximately 6 miles of 36-in. pipeline right-of-way in Wetzel County, West Virginia. Headquarters is Ellenboro, West Virginia. The superintendent is Tyson L. Schook. Approximate start date: July 9.

Pe Ben USA Inc. was awarded a contract by Euraz Tubular to offload 72,000 ft of 12-in. pipe in Wharton County, Texas. Headquarters is Boling-Layo, Texas. The superintendent is Blake Culp. Approximate start date: July 9.

Right-of-Way Clearing & Maintenance Inc. was awarded a contract by Hanging H Companies for clearing on 1,500 ft of 24-in. pipeline right-of-way in Noble County, Ohio. Headquarters is not yet determined. The superintendent is Rick Brown. Approximate start date: July 9.

United Piping Inc. was awarded contracts by BP Pipelines for 1.) the inspection of a 12-in. pipeline at Laura Station in Peoria County, Illinois. Headquarters is on the jobsite. The superintendent is Jim Bailer. Approximate start date: July 9, 2018; and 2.) potholing excavation work in Dubuque County, Iowa. Headquarters is on the jobsite. The superintendent is Jim Bailer. Approximate start date: July 9.

Environmental Reclamation Solutions (EnRec) was awarded a contract by Precision Pipeline LLC for environmental work on approximately 32 miles of 42-in. pipeline right-ofway in Giles and Montgomery Counties, Virginia. Headquarters is Pembroke, Virginia. The superintendent is Randy Rubenzer. The starting date is July 2.

T.G. Mercer Consulting Services Inc. was awarded a contract by ONEOK for pipe yard construction and the offloading and racking of approximately 100 miles of 24-in. pipe and 300 miles of 30-in. pipe in Wichita, Clay, Hood, Houston and Liberty Counties, Texas. Headquarters is Willow Park, Texas. The superintendent is Michael Magee. Approximate start date: July 2.